Cebu sports complex to open early next year
THE Cebu Provincial Sports Complex is expected to open in the first quarter of 2027, more than five years after the facility was declared complete in 2020 but remained unused.
Gov. Pamela Baricuatro announced the target opening, following questions about the facility's prolonged non-utilization and deteriorating condition raised in the 2025 Commission on Audit (COA) report.
“This has been addressed already. In fact, it will be completed by the first quarter of next year,” Baricuatro said in a mix of English and Cebuano.
The provincial government plans to use the facility for basketball and pickleball, as well as provide a training hall for athletes, Capitol officials said.
Located on a province-owned property in Sitio Sudlon, Barangay Lahug, Cebu City, the sports complex underwent groundbreaking in October 2018 under the administration of former governor Hilario Davide III.
COA records showed that the provincial government initially awarded the project for P19.96 million in September 2018. Its cost later increased to P21.84 million following a variation order.
The project had an initial implementation period of 165 days, which was extended by another 60 calendar days. The provincial government certified it as 100 percent complete on Jan. 9, 2020.
However, a COA inspection on Aug. 7, 2025, found that the facility had never served its intended purpose and was instead being used mainly as storage for construction materials for other infrastructure projects.
Auditors also observed damage in several portions of the building, raising concerns about its deteriorating condition despite the presence of an assigned security guard.
The Provincial Engineering Office told auditors that the facility had been completed before Typhoon Odette struck Cebu and allegedly damaged parts of the structure.
However, the office admitted it had not conducted a comprehensive assessment of the damage.
COA also flagged the project's financial documentation, noting that the provincial government had paid the contractor P16.31 million through an advance payment and three progress billings between November 2018 and January 2020.
Despite the completion certification, the project remained under the government's Construction in Progress accounts because the contractor had yet to submit a request for final payment, according to the Office of the Provincial Accountant.
Auditors also identified missing project documents, including an approved construction safety and health program concurred by the Department of Labor and Employment, proof of invitations to procurement observers and proper photographic documentation supporting the third billing.
COA warned that the facility's prolonged non-use could lead to further deterioration and additional government spending for repairs and rehabilitation.
During the audit exit conference, the Provincial Administrator told auditors that the Provincial Sports Commission was interested in using the facility as a regional gymnastics training center.
However, discussions were still ongoing over who would shoulder the expenses needed to make it operational.
The Provincial Engineering Office also clarified that the project remained under Phase I.
Meanwhile, Baricuatro said the provincial government was also considering a much larger sports facility comparable to major sports centers in Subic and Clark.
“We really intend to build a bigger one like the ones in Subic and Clark — that massive of a sports center,” she said.
Baricuatro said the Capitol was still evaluating possible locations for the proposed development, with northern Cebu previously identified as a potential site.
She added that the Philippine Sports Commission had expressed interest in providing an initial allocation of P1 billion for the proposed sports facility as the provincial government pursues its goal of developing Cebu into a major sports tourism destination.(MyTVCebu)